Commissioning Services for West Addition

Delnor Community Hospital

Geneva, Illinois

 

This addition to the existing facility provides expansion space for the Hospital\'s radiology department on the first floor and patient rooms on the second and third floors. The basement and penthouse contains the MEP equipment to support this project as well as future expansions of the hospital.

Henneman Engineering is providing commissioning services for all MEP systems and equipment including temperature controls, chillers, boilers, pumps, air handling units, cooling towers, heat exchangers, domestic hot water system, fire protection, fire alarm, normal and emergency power, emergency generator, nurse call and telecom systems.

Henneman was also retained as the MEP master planning engineer for Delnor Community Hospital.

Completion Date
2008

Square Feet
98,000 square feet

Total Construction Cost
$28,000,000